Road Construction Updates

Construction of our section of Cold Spring Rd from the intersection of Carnes Rd moving south 5,600 feet.  Construction prep to begin Sept 14, pulverizing Friday 9-17 into Saturday 9-18..  Paving 9/23-9/24. 


Poeppel Rd, from intersections of Poeppel/Pond Road to Poeppel/Star School roads. Milling of butt joints- done Sept 14,  Paving scheduled 9/23-9/24.