Road Construction Updates Week of September 27th

Payne and Dolan moved back in this morning to do surface on Hoge Road.  The plan is to have it all done by the end of the week.

It is projected to go like this:

  • Monday – Hoge Road
  • Tuesday – Finish Hoge Road if needed, then Star School Road 
  • Wednesday – Koshkonong Lake Road and possibly Fairway Road
  • Thursday – Fairway Road then off to Potowattomi and Blackhawk Bluff.  
  • Friday – Finish up